Project Overview

This project involved a broad range of early-stage construction activities to prepare the corridor for future highway improvements.

Work included clearing and grubbing, invasive plant removal, and stripping and disposal based on site conditions. Our team completed embankment construction using import material to support design and performance requirements for the project.

The scope also included the installation and monitoring of geotechnical instrumentation, as well as the careful relocation of existing MoTI and Rogers fibre optic infrastructure to accommodate upcoming works.